Canal operationsResearch insight

Ship counts can miss a slowdown at the Panama Canal

Research insight · Based on descriptive findings · Not peer reviewed

The Panama Canal handled 979 oceangoing transits in September 2026, just 1.5% fewer than a year earlier. But average Canal Waters Time rose from about 21 to 38 hours.

Transit counts tell you how many ships got through, not how long it took them. The Canal’s time measure starts when a ship is declared ready and ends at completion. It does not start at arrival. To judge how the route is performing, track the count and the clock together.

Comparable counts, very different time

Each September from 2022 to 2026, transit counts stayed between 958 and 999. Average Canal Waters Time ranged from about 20 to 50 hours.

YearCWT · hoursTransits
2022
37.18 h
999
2023
50.23 h
977
2024
20.20 h
958
2025
21.40 h
994
2026
37.97 h
979
Bars start at zero; common scale 0–60 hours. Right-hand figures are oceangoing transit counts, not a second plotted scale. Source: ACP monthly operations summaries, page 1 (2022 · 2023 · 2024 · 2025 · 2026). One reporting authority, not five independent sources.

Fewer transits in the widest beam group

In September 2026, transits in the ≥107 ft beam group fell 9.4% year on year; the combined narrower groups rose 1.9%. The widest group also had the largest August-to-September daily decline in this five-year window. Draft restrictions had already stepped down to 49.5 ft on 3 July and 49 ft on 24 July, then 48.5 ft on 15 August. The 48 ft limit took effect on 2 September; daily reserved slots were reduced to 34 for booking dates from 4 September, then 32 from 15 September.

Beam describes a ship’s width, not its lock assignment: some ships between 106.2 and 108 ft can use the Panamax locks with prior approval and draft no greater than 37 ft.

High time is not a diagnosis

September 2022 offers a useful comparison: 999 transits, and average Canal Waters Time of 37.18 hours, close to September 2026. The Canal had its full 50 ft draft available, but ACP records a completed nine-day Gatun west-lane outage, 30 August–7 September, with estimated Panamax capacity of 21–23 vessels per day, as well as shorter outages.

In 2026, March–May transit counts were the highest for those months in the five-year comparison. Canal Waters Time rose in April, before the summer draft and booking changes. In August and September, transit counts were less buoyant, Canal Waters Time was higher, and restrictions were in force.

In 2024, delay eased before traffic picked up

During the 2023–24 drought, average Canal Waters Time fell from 44.1 hours in December to 20.9 hours in February. Both months recorded 23.7 arrivals a day, but February actually had fewer completed transits: 22.8 a day, down from 24.1. In-transit time stayed near 10 hours. Later, completed transits rose from 24.1 a day in March to 26.3 in April, with just another half-hour drop in Canal Waters Time.

Most of the drop in Canal Waters Time preceded the March 18 and 25 Panamax slot additions, which overlapped with lock maintenance. The January increase came with a change in reservation rules. The sequence shows why the two measures are worth tracking separately: time can fall before throughput recovers.

What the figures can’t tell us

How long ships waited

ACP defines Canal Waters Time as running from when a vessel is declared ready for transit until it completes its transit (ACP 2019 annual report, p. 30). It includes more than waiting. Average In-Transit Time rose from 11.30 to 11.59 hours. The two clocks cover different parts of the passage, and the published averages may cover or weight vessels differently. Subtracting one from the other would not isolate a wait.

A different clock starts before the lock. Chico and colleagues use vessel tracks to estimate time from an observed stop in the Canal approaches to arrival at the first lock (open methods preprint). That interval can start before declared readiness and ends before transit is complete. Our radar snapshots answer a different question again: how many targets were present at the time of the pass. None of these measures can substitute for the others or identify a vessel’s booking status on its own.

What drove the September change

The monthly figures can’t separate the effects of water, maintenance, booking rules and vessel mix. The advisories report the rules in force, not vessel compliance. Comparable ships may have spent longer between declared readiness and transit, or the mix of booked and unbooked ships may have shifted. Both could be true. Daily counts and timestamps for readiness, transit start and completion, split by reservation status and vessel class, would help distinguish them.

Related methods. Chhetri and colleagues show how average time at port can hide variation across vessels. Their measure is not Canal Waters Time. With comparable vessel-level records, the median and 90th percentile within booking and vessel classes would help distinguish a change in typical reported time from a change among the longest cases. The monthly averages, highs and lows do not provide those percentiles.

Whether service recovered in October

Several October 2026 traffic fields repeat October 2025 exactly; time figures closely resemble them at different precision. Booking and staffing fields differ. We leave the repeated fields unconfirmed rather than use October as evidence of recovery. Historical waits for unbooked ships would give another comparison.

Transit counts cover completed crossings, not ships that chose another route. They don’t establish cargo delivered or customer costs.

Evidence and corrections

The 17 November erratum records the changes to the maintenance summary, time definition and draft/booking chronology. The September chart and its reported figures are unchanged. The 20 November follow-up adds a separate historical comparison for December 2023 to April 2024. Historical working notes and the research workbook are preserved separately rather than distributed as reader-facing downloads.

21 November: Methods companion linked. See Two clocks at the Panama Canal for how ACP defines Canal Waters Time and In-Transit Time, and for the Neopanamax booking changes that applied to booking dates from 13 September.

Companion notes

What port queue counts can miss compares the end of the Los Angeles and Long Beach backlog with berth stays at Los Angeles.

Feedback and corrections

Corrections, alternative interpretations and relevant source material on Canal traffic and time measures are welcome. See how we handle corrections and review.

How to cite

Daley, Matthew. (2026, November 16). Ship counts can miss a slowdown at the Panama Canal. CEVE Research.